I am getting my 1960 back from body and paint next week and will be starting finish assembly. The body is on a rolling chassis (rear end, front and rear suspension, etc are all done), but the engine and transmission are not in the car. I need some feedback from those of you who have put together a C1, particularly 58-60. I want to try and not have to re-do anything by not following a correct sequence.
Of course I have looked at the AIM, and I may be wrong, but not sure how it could have been the installation sequence followed during the original assembly, e.g. body mounting comes before suspension in the AIM.
So if you have experience please let me know if you see any flaws in my logic.
1. Install firewall insulation
2. Install wiring (dash, front and rear harnesses)
3. Install stuff mounted in the engine compartment and firewall, e.g. voltage regulator, horn relay, wiper motor (wait to install wiper transmissions as I have read that it is easier to get the windshield assembly in with the wiper transmissions not installed)
4. Install exterior trim including top fender, side spears, side emblems, fender and door trim. (easier to do these before guts are back in the doors and kick panels are in place.
5. Install Dash Pad, defrost bezels, speaker grill, grab bar and related
6. Install Windshield
7. Install wiper transmission and other wiper related parts under the dash
8. Install Heater/Defroster
9. Install Cowl Vent and lever assemblies
10. Install Pedal assembly and related parts. e.g. clutch rod)
11. Install Master Cylinder
12. Install Park Brake and Hood release (and related parts)
13. Install Gauge Cluster (including all the attachments that go through the firewall, e.g. oil line, speedo cable, tach cable, etc.)
14. Install Steering (steering plate to the firewall, steering gear/shaft assembly firewall seal etc are all installed)
As far as I can tell, everything else to finish can be done in any sequence without having to go back and re-do anything (take something back apart).
I will probably install the engine and transmission last.
Thanks,
Don
Of course I have looked at the AIM, and I may be wrong, but not sure how it could have been the installation sequence followed during the original assembly, e.g. body mounting comes before suspension in the AIM.
So if you have experience please let me know if you see any flaws in my logic.
1. Install firewall insulation
2. Install wiring (dash, front and rear harnesses)
3. Install stuff mounted in the engine compartment and firewall, e.g. voltage regulator, horn relay, wiper motor (wait to install wiper transmissions as I have read that it is easier to get the windshield assembly in with the wiper transmissions not installed)
4. Install exterior trim including top fender, side spears, side emblems, fender and door trim. (easier to do these before guts are back in the doors and kick panels are in place.
5. Install Dash Pad, defrost bezels, speaker grill, grab bar and related
6. Install Windshield
7. Install wiper transmission and other wiper related parts under the dash
8. Install Heater/Defroster
9. Install Cowl Vent and lever assemblies
10. Install Pedal assembly and related parts. e.g. clutch rod)
11. Install Master Cylinder
12. Install Park Brake and Hood release (and related parts)
13. Install Gauge Cluster (including all the attachments that go through the firewall, e.g. oil line, speedo cable, tach cable, etc.)
14. Install Steering (steering plate to the firewall, steering gear/shaft assembly firewall seal etc are all installed)
As far as I can tell, everything else to finish can be done in any sequence without having to go back and re-do anything (take something back apart).
I will probably install the engine and transmission last.
Thanks,
Don
Comment